Low water levels  in Mumwemwe dam

Mumwemwe dam visit

  DAY TWO FIELD VISIT Date 20 February 2016 Day 2 Mumwemwe dam wall was raised and widened as a way of increasing the capacity. Stone pitching was done on both side and at the top to reduce cattle traction. 8 silt traps were constructed to reduce siltation of the dam. The dam benefits 425

murove irrigation1

Murove irrigation visit

DAY TWO FIELD VISIT Date 20 February 2016 Day 2 Murove irrigation LED Representative Mrs. Artzinger Mr. Masukume the Programme Managing Director, Mrs. Mbiza the Training and Community Development Manager and Mr. Tawanda Shonhiwa the field officer visited Murove irrigation to assess project progress. The project members planted green maize in December 2016 using irrigation